June 14, 2014
![](2014garden/20140614/IMG_0509.JPG)
The weather wasn't quite as sunny today, but work continued on the second bed.
![](2014garden/20140614/IMG_0510.JPG)
The beds were separated by four feet to accommodate a walkway.
![](2014garden/20140614/IMG_0511.JPG)
I decided to create the walkway by salvaging brick discarded by the former homeowner.
![](2014garden/20140614/IMG_0512.JPG)
The frame of the second bed is constructed the same way as the first.
![](2014garden/20140614/IMG_0513.JPG)
The composite posts are going in.
![](2014garden/20140614/IMG_0515.JPG)
The aluminum strapping is installed in the second bed.
![](2014garden/20140614/IMG_0516.JPG)
A view of the constructed second bed.
![](2014garden/20140614/IMG_0517.JPG)
A view of the aluminum strapping.
![](2014garden/20140614/IMG_0518.JPG)
The beds are level, but the ground is not. The backs of the beds will be taller than the fronts.
![](2014garden/20140614/IMG_0519.JPG)
The second bed is filled with garden soil. The dirt pile in the back is getting lower.
![](2014garden/20140614/IMG_0521.JPG)
![](2014garden/20140614/IMG_0524.JPG)
![](2014garden/20140614/IMG_0525.JPG)
Work now turns to the walkway. First, the ground is graded and loose soil and stones removed.